YPF10 (before lunar new year)




















Tilted starter bars are being rectified by HH (70% completed).
Formwork to screen wall (B2/F to B1/F) (B1/F to G/F, ramp area) are being carried out.
Concreting of Column C29 and C39 (scheduled on 31 Jan 2011).
Modification of existing hoarding at Yip Po Fong Street was completed.
Re-location of Bus Stop was completed.
HH was reminded to provide alternative waterproofing method in case of not using waterstop.
......orz